Step-by-step installation and configuration instructions

You need to complete steps 1 to 7 in order to install the HortiMaX-Go!. You then need to complete steps 8 to 14 in order to carry out the configuration.

Step Description
1

Unpack the required materials and check for defects.

2

Examine the descriptions included with the equipment.

3

Assign addresses to all Smart Switches using the instructions provided on the address list, zone and product stickers.

4

Install the motor control boxes (MCBs), and then mount the Smart Switches in the desired locations.

5

Use the bus cable (type: UTP Cat5e AWG24 cable) to connect the Smart Switches and the controller in series. Install terminal resistors on the first Smart Switch and the last one.

6

Connect the DC24V power supply (or supplies). Then interconnect the DC24V- of each power supply, and connect this to the ground (earth) terminal.

7

Activate the HortiMaX-Go! and the Smart Switches by switching the supply voltage on.

8

When the HortiMaX-Go! is configured for the first time, the display will show start menu. Select the desired language and unit of measurement. Tap confirm ‘'.

9

On the scanning screen, tap the Scan button ‘'. The system will detect the connected Smart Switches automatically.

10

Check whether all the connected Smart Switches are in the address list and there are no address conflicts or other problems.

11

Disable any valves and start contacts that are not connected, then disable any valve groups that are not required.

12

Configure the system settings, such as location, time and IP address.

13

Configure all the connected 'open-close' systems by entering the required settings, such as the run times and opening directions.

14

Calibrate the EC and pH sensors using the calibration solution provided. Follow the instructions on the display.